Posts tagged Single-Ply
Anderson Family Health & Dental Center

Here, we installed a single-ply Sika Sarnafil 60-mil mechanically attached PVC with 24 gauge coping, LASTOBOND peel and stick underlayment, and an AEP Box Rib metal roofing with associated siding and flashing.

Westwood Village

We used mechanically attached single-ply TPO over ¼ inch secure rock with a 20-year labor-and-materials warranty and a new Kynar 24 gauge with ANSI Clete. In total, this project was 120,000 square feet.

Maywood Middle School

Corning’s Maywood Middle School called for removal of the existing hail damaged, twenty-year-old PVC roof. We applied a new 60-mil PVC roof with a 20-year labor-and-materials warranty.

Corning High School Gym

We tore off an EPDM roof, replaced damaged and wet insulation, and installed a mechanically attached 60-mil PVC roof with walk pads under a 20 year labor-and-materials warranty.

Shasta Trinity Medical Center

We removed the existing built-up roof and tile mansard. We installed a new ½ inch secure rock under a mechanically attached 60-mil PVC with a 20-year labor-and-materials warranty. This was a 17,500 square foot project and we used Kynar 24 gauge with ANSI Clete.

Sheraton Hotel

We roofed the Sheraton Hotel by the Sundial Bridge in 2017. It has a single-ply TPO roof of 45,000 square feet.

Junction Elementary

We completed a total reroof of all eleven buildings at Junction Elementary. It was a 70,000 square foot job, which we completed in under a month.

Shasta Community Health

Shasta Community Health Center contracted Harbert Roofing throughout 2015 and 2016 to complete their single-ply roof of 15,000 square feet along with 12,000 square feet of metal siding.

View 202

We installed 7,000 square feet of single-ply and 2,000 squares of metal siding, amounting to a contract of $175,000. 

 

California Building

We roofed these office buildings, consisting of single ply and RHEINZINK rain screen metal panels. The contract totaled $310,000.

Cypress Plaza
Cypress Plaza commercial center, featuring a single-ply roof membrane, metalwork, subgrade waterproofing, and coping installed by Harbert Roofing in 2007.

Cypress Plaza is a commercial multi-use center built in 2007. Harbert Roofing was responsible for supplying and installing a single-ply roof membrane, metal, subgrade waterproofing, and coping. The project consisted of installing:

  • GenFlex 60-mil TPO membrane over six inches of Western Insulfoam with secure ply over metal decking';

  • A Western Insulfoam cricket system;

  • Metal Sales vertical seam roof in Marine Green;

  • A fabricated built-in gutter system of clad metal and single-ply membrane;

  • Waterproofed elevator well with Grace PreProof, Grace Bituthene 4000, and Hydroduct 220;

  • A built-up roofing system using a base, two-ply, and a cap over non-conditioned space;

  • Deck waterproof with a GacoFlex elastomeric coating.